RECOMMENDATIONS OF THE ADMINISTRATION Ð June 23, 2003

 

 

4.      Authorization to Expend 1998 Bond Funds Ð Donegan Elementary School

         Construction Project

 

 

INFORMATION:

 

The Donegan Elementary School Project was completed in November 2001 after a six-month time extension due to stability issues of the existing building demolition and an extremely wet 2000 summer. The electrical contractor, Medlar Electric, has agreed to closeout the project with payment to them of $43,929 for additional prevailing wage cost increases, field supervision, and field project costs. In addition, Medlar Electric has agreed to a change order credit for unused project material allowance and a telecommunication credit of $17,181.25. There was also a previous change order processed for permit fees of $1,649; therefore, there is a net cost increase to the original contract amount of $28,396.75.

 

 

RECOMMENDATION:

 

That the Board of School Directors authorize a change order be processed for the net cost of $26,747.75 to Medlar Electric for the following:

 

a. Prevailing wage cost increase, field supervision, and field project cost due to

the project completion time extension ($43,929).

 

b. Change order credit for unused project material allowance and

telecommunication credit (-$17,181.25).

 


Table of Contents

Minutes

The administration's recommendations 1, 2, 4, 5, 6, 7, 8, 9, 10, 11, 12,
13, 14, 15, 16, 17, 18, 19, 20, 21, 24, 25, 27, 28, 29, 30, 31, 32, 33,
34, 34a, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50,
51, 52, and 53 were considered together.