RECOMMENDATIONS OF THE ADMINISTRATION - January 27, 2003
INFORMATION:
The existing cooling tower has been removed. Investigative probes of the surface below the old cooling tower revealed that soft and yielding materials below must be removed prior to installation of the new foundations and equipment. The contractor, Worth and Company, Inc., will over excavate the area below the old cooling tower and replace the material with new compacted stone for a cost not to exceed $5,000.
RECOMMENDATION:
That the Board of School Directors issue a change order to Worth and Company, Inc., for a cost not to exceed $5,000 to over excavate the area below the old cooling tower and replace the material with new compacted stone.
The administration's recommendations 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 16, 18, 19, 20, 21, 22, 23, 24, 25, 26, and 27 were considered together.