RECOMMENDATIONS OF THE ADMINISTRATION - January 27, 2003
INFORMATION:
The paving project at Calypso Elementary School is completed. The project material allowance on this project is $2,240. The contractor, S & G Paving, has agreed to issue a change order deduct in this amount.
RECOMMENDATION:
That the Board of School Directors issue a change order credit in the amount of $2,240 to S & G Paving for the unused project material allowance.
The administration's recommendations 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 16, 18, 19, 20, 21, 22, 23, 24, 25, 26, and 27 were considered together.