RECOMMENDATIONS OF THE ADMINISTRATION - March 18, 2002
INFORMATION:
As part of the Capital Improvement Plan, the board approved the demolition of the recently acquired property at 256 East Fairview Street, Bethlehem, adjacent to the maintenance building. Prior to going out for bids, asbestos testing is required. AWTEC has agreed to do this testing for a cost not to exceed $850.
RECOMMENDATION:
That the Board of School Directors approve a contract to AWTEC for asbestos testing at 256 East Fairview Street, Bethlehem, prior to its demolition, for a cost not to exceed $850.
The administration's recommendations 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 19, 20, 21, 22, 23, 24, 25, 26, 27, 29, 30, 31, 33, and 34 were considered together.