RECOMMENDATIONS OF THE ADMINISTRATION - February 25, 2002

 

 

4.      Authorization to Expend 1998 Bond Funds - William Penn Elementary

School Roof Replacement Project - Change Order Deduct

 

 

INFORMATION:

 

The William Penn Elementary School Roof Replacement Project is complete. The contractor, Alan Kunsman Roofing and Siding, has agreed to issue a credit in the amount of $3,062.50 for unused material allowance.

 

 

RECOMMENDATION:

 

That the Board of School Directors authorize a change order deduct to Alan Kunsman Roofing and Siding for unused material allowance at the William Penn Elementary School Roof Replacement Project, for a credit in the amount of $3,062.50.

 

 


Minutes


Table of Contents