RECOMMENDATIONS
OF THE ADMINISTRATION – January
29, 2001
INFORMATION:
The
ceiling tile installation at the Freemansburg Elementary School Remediation
Project is substantially completed.
The contractor, Duggan & Marcon, Incorporated, did not completely
utilize the material allowance on the project and has agreed to issue a change
order deduct in the amount of $4,740.
RECOMMENDATION:
That the Board of School Directors authorize a change
order deduct to Duggan & Marcon, Incorporated, for material allowance not
completely utilized in the installation of ceiling tiles at the Freemansburg
Elementary School Remediation Project, realizing a credit of $4,740.
The administration's recommendations 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, and 28 were considered together.