RECOMMENDATION OF THE ADMINISTRATION - March 20, 2000

  1. Authorization to Expend Capital Funds - Governor Wolf Elementary
    School's Renovation/Construction Project - Change Order Details

INFORMATION:


During the course of construction at the Governor Wolf Elementary School, the
administration was informed that a plenum (air return) ceiling would be installed in the
school. In order to comply with fire codes, the data network requires plenum-rated cable
(approx. 38,000 ft.) instead of non-plenum cable.In the event of a fire, plenum cable
reduces the danger of toxic fumes from cable insulation being spread through air returns.
The contractor, Orlando Diefenderfer Electrical Contractors, Inc., has agreed to install
plenum cable for a cost not to exceed $10,206.00.

In addition, cable labeling and documentation needs to be completed.
agreed to perform this labeling at a cost not to exceed $1,542.35.


RECOMMENDATION:

The contractor has

That the Board of School Directors issue a change order to Orlando Diefenderfer Electrical
Contractors, Inc., to:

  • install plenum-rated data cable in Governor Wolf Elementary School at a cost
    not to exceed $10,206.00 and,
  • complete cable labeling and documentation at a cost not to exceed $1,542.35.

Table of Contents

Minutes

The administration's recommendations 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13,
14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 25, 26, 27, 28, 29, 30, 31, and 32 were
considered together.